Arab Potash CompanyCompleted

Thickener Rake Drive System Modernization

Instrumentation engineering and site coordination for the modernization of three thickener rake drive systems during a five-day shutdown.

Project figures

Thickeners modernized
3
Shutdown days
5

Engineering challenge

The original mechanical drive arrangements posed maintenance and reliability limitations.

Role and responsibilities

Coordinated instrumentation engineering, reviewed detailed engineering, supervised field installation, and coordinated parallel teams, SAT, commissioning, and handover.

Technical approach

Integrated instrumentation into the hydraulic rotation drive upgrade using pressure-based torque monitoring, rake position measurement, and local panel interfaces.

Execution

Staged parallel installation and coordinated functional tests, equipment protection checks, and safety interlock verification before handover.

Results

Commissioned and handed over the modernized systems with improved equipment protection and maintainability.

Engineering lessons

Define acceptance checks for measurement, equipment protection, and local panel interfaces during engineering review so parallel installation teams share the same handover criteria.