Project figures
- Plant areas covered
- 4
Engineering challenge
The migration spanned the blending yard, wet yard, pump house, and main beneficiation plant. The field devices and industrial communications had to be verified across all four areas.
Role and responsibilities
Supervised contractor work, coordinated field execution, and verified instrumentation signals, communications, equipment functionality, and safety interlocks for commissioning acceptance.
Technical approach
Used field checks by plant area to confirm that signals reached the migrated control system and that the equipment fulfilled the expected functions.
Execution
Coordinated contractor activity and verified field functionality through commissioning acceptance.
Results
The scope of field verification and commissioning acceptance covered four plant areas.
Engineering lessons
Plan acceptance around end-to-end field verification when a controls migration spans multiple operating areas.