Project figures
- Shutdown days
- 10
- Field instruments
- 50+
- Cables
- 100+
- Internal employees and subcontractor personnel coordinated
- 4 + ~15
Engineering challenge
Aging equipment, obsolete components, and a legacy design limited maintenance and troubleshooting. Work had to fit a restricted shutdown window.
Role and responsibilities
Led instrumentation execution, prepared the scope and job packages, coordinated subcontractors, prepared cable schedules, junction box and termination drawings, and verified equipment readiness.
Technical approach
Prepared field work in advance and coordinated instrumentation interfaces with the controls team. The wider migration from Siemens S7-400 to S7-1500 included safety I/O and integration with ABB System 800xA over PROFIBUS.
Execution
Supervised dismantling, installation, and instrument integration, followed by vendor-assisted commissioning and operational handover.
Results
Completed the instrumentation execution on schedule and handed over the modernized equipment after commissioning.
Engineering lessons
Verify interfaces, equipment readiness, and contractor work packages before the shutdown so installation and commissioning can follow a clear sequence.