Arab Potash CompanyCompleted

Heavy Fuel Oil Skid & Burner Management System Modernization

Field instrumentation leadership for replacing an obsolete heavy fuel oil skid and its associated Burner Management System during a ten-day shutdown.

Project figures

Shutdown days
10
Field instruments
50+
Cables
100+
Internal employees and subcontractor personnel coordinated
4 + ~15

Engineering challenge

Aging equipment, obsolete components, and a legacy design limited maintenance and troubleshooting. Work had to fit a restricted shutdown window.

Role and responsibilities

Led instrumentation execution, prepared the scope and job packages, coordinated subcontractors, prepared cable schedules, junction box and termination drawings, and verified equipment readiness.

Technical approach

Prepared field work in advance and coordinated instrumentation interfaces with the controls team. The wider migration from Siemens S7-400 to S7-1500 included safety I/O and integration with ABB System 800xA over PROFIBUS.

Execution

Supervised dismantling, installation, and instrument integration, followed by vendor-assisted commissioning and operational handover.

Results

Completed the instrumentation execution on schedule and handed over the modernized equipment after commissioning.

Engineering lessons

Verify interfaces, equipment readiness, and contractor work packages before the shutdown so installation and commissioning can follow a clear sequence.

Illustrative gallery

Illustrative steel process piping and field instrumentation
Generic illustration of industrial equipment.
Instrumentation delivery sequence
  1. Prepare shutdown scope and work packages
  2. Supervise installation and instrument integration
  3. Verify instrumentation during commissioning
  4. Hand over to operations